• Join our team
    • Jobs
  • Meet us there
  • Send us a message
  • Learn about IAI

IAI

Clean Water Solutions

  • facebook
  • linkedin
  • youtube-play
  • email-alt
  • Services
    • Contract Operations, Maintenance & Management
      • Wastewater Treatment
      • Drinking Water Treatment
      • Certified Operators
      • Small Systems
      • Water & Wastewater Process Engineering
      • Mechanical Services for Water & Wastewater Utilities
    • Dredging
      • Environmental Dredging
      • Lagoon Sludge Removal
    • Sediment Dewatering
      • Geotextile Tube Dewatering
      • Geotextile Tube Dewatering Test (GDT)
      • Sediment Remediation
      • Mechanical Dewatering
      • Dewatering & Water Treatment Systems Design
    • Dredging Water Treatment
      • Mobile Water Treatment System
    • Wetlands & Shorelines
      • Shoreline Protection
  • Projects
    • Contract Operations
    • Dredging
    • Sediment Remediation
    • Geotextile Tube Dewatering
    • Mechanical Dewatering
    • Dredging Water Treatment
    • Wetlands & Shorelines
    • Coal Ash
  • News
  • Jobs
  • Conferences
  • About Us
  • Contact Us
You are here: Home / Projects / Dredging / Portage Canal Segment 1 Dredging

Portage Canal Segment 1 Dredging

August 3, 2018 by IAI

Aerial view of the project site, just prior to the start of dredging
Aerial view of the project site, just prior to the start of dredging
Placing the sand cap in the canal via IAI's custom built sand slurry dispersion system
Placing the sand cap in the canal via IAI's custom built sand slurry dispersion system
Debris removal operation
Debris removal operation
Geotextile tube dewatering pad construction
Geotextile tube dewatering pad construction
Dredging the canal
Dredging the canal
Launching IAI's 8" auger dredge in the canal
Launching IAI's 8" auger dredge in the canal
Loading sand into the slurry box for the capping operation
Loading sand into the slurry box for the capping operation
Geotextile tubes dewatering
Geotextile tubes dewatering
Raking debris from the canal using an excavator
Raking debris from the canal using an excavator
« ‹ 1 of 4 › »

Tailored Sediment Removal and Treatment Equipment Make a Big Impact on a Small Project

“Use the correct tool for the job,” is a common construction safety rule, reminding us that the right equipment, used properly, will produce the safest, most efficient result. Not only is it important to use the right type of equipment, but also the right size.

The Portage Canal Segment 1 Dredging Project is a prime example of this principle. The canal, from Dewitt to Adams Streets, in Portage, WI, required dredging to remove metals-contaminated sediment. The placement of material in the canal and type of contamination was well suited to hydraulic dredging and geotextile tube dewatering, and water treatment; however the canal is very narrow, and at the time of this project, was flanked on two sides by unrelated building construction.  The total volume of material to be removed was relatively small, only about 600 cubic yards. The dredging contractor would need to provide a system, scaled to work within the confinements of the canal, as well as the access and support areas; in other words, to use the correct tools for the job.

Fully Self-Performed Dredging Project

IAI was selected as the low bidder, and self-performed the full project: providing dredging, geotextile tube dewatering, water treatment and sand capping services.  IAI’s small, custom-built 8-inch diameter auger dredge with a cable drive system was a perfect fit for the narrow canal:

  • The linear alignment of the canal simplified cable installation
  • Dredge positioning was accomplished by cable placement – no RTK/GPS positioning required
  • Shallow water depths and limited access area did not impede the small auger dredge

IAI was tasked with hydraulic dredging to remove the contaminated sediment from the canal, conditioning the dredged material, dewatering the material in geotextile tubes, treating the water released from the tubes and placing a sand cap in the canal at the conclusion of dredging operations.

Customized Equipment

Another custom solution developed by IAI’s crew involved raking the canal for large debris. Debris was raked from the canal bottom using a skeleton bucket, mounted on an excavator, staged on a floating barge.

Sediment Conditioning

Sediment conditioning consisted of injecting the dredge slurry with a cationic emulsion polymer product. The polymer formed sticky floc particles in dredge slurry, attracting solids and repelling water. As the dredge slurry-polymer mixtures flowed through the pipe runs to the dewatering pads, the turbulence homogenized the dredge slurry-polymer mixture and increased the size of the floc particles as more solids were attracted to them.

IAI’s operators performed regular checks of the floc formation in the dredge slurry, and combined with their observation of the performance of the geotextile tubes, and regular communication with dredge, the operators were able to tweak the applied polymer dose, as needed to achieve proper conditioning of the dredge slurry.

Geotextile Tube Dewatering

In the dewatering pads, large circumference geotextile tubes were utilized to dewater and contain the dredged material until disposal. The dredge slurry-polymer mixture was directed into the geotextile tubes via a network of HDPE main header pipe, hoses to the fill ports of the tubes, and flow control valves.

A total of three (3) geotextile tubes were filled over the course of the project, to dewater 900 cubic yards of material. Tubes were filled at a rate of approximately 3 – 5 days per tube. Each tube was 60-ft. in circumference and 100-ft. long. The geotextile tubes were allowed to passively dewater for eight (8) days after the conclusion of dredging, and then were dry enough to be removed from the site without the addition of amendment. Preliminary testing had indicated a minimum of (12) days of dewatering would be required to achieve in-situ percent solids.

IAI operators use a protocol of observation and data tracking to evaluate the performance of each geotextile tube as it is filled. Operators note the flocculation, thickness and composition of the material flowing into the tube, the volume and appearance of water shedding off the exterior of the tube, and the rate at which the tube height is increasing. When a geotextile tube reaches the maximum fill height designated by the manufacturer, flow to that tube is stopped and the tube is allowed to passively dewater for a period of time. The length of time required for passive dewatering depends mostly on the volume of consolidated material already inside the tube. This protocol has been developed over many years of utilizing geotextile tubes to dewater contaminated sediment.

Dredging Water Treatment

Geotextile tube filtrate and storm water collected in the dewatering pad sump were treated in a temporary water treatment plant, designed, installed and operated by IAI. The plant was oversized, with capacity to handle up to 1,200 gallons per minute of incoming flow, and utilized bag filters to remove solids. Over the course of the dredging project, nearly 3.7 million gallons of water were treated and discharged to the sanitary sewer, at a maximum permitted rate of 400 gpm.

Discharge from the treatment system was regulated by an Industrial Pretreatment Permit issued by the local municipality. IAI provided a skilled operations staff to ensure optimal treatment plant operations.

Sand Cap Placement

At the completion of dredging operations, IAI mobilized its alternative bid, sand slurry dispersion capping system to the site. It was another example of the use of small, custom-built equipment on the project, specifically tailored to the requirements of the site. A minimum 6-in. sand cap was placed throughout Segment 1 of the canal, to isolate and prevent any remaining trace mercury contamination from being transported out of the canal.

Remedial Goals Exceeded

The primary contaminants of concern addressed by this project were mercury (Hg) and lead (Pb), with mercury being the primary risk driver. Elevated levels of other contaminants such as polycyclic aromatic hydrocarbons (PAHs), petroleum substances, and polychlorinated biphenyls (PCBs) were also detected in the canal prior to remediation.

Post-dredge and post-capping analysis showed the remedial action removed 70% of the mass and volume of mercury or approximately 8-lbs. of mercury (Hg). The remedial action also reduced the volume and mass of co‐occurring contaminants, such as lead (Pb). The surface weighted average concentration (SWAC) showed a 70% reduction in mercury concentration, post-dredge. After sand placement, the final SWAC of 0.02 mg/kg total mercury is far below the remedial goal of 0.36 mg/kg total mercury. The Wisconsin Department of Natural Resources (WDNR) Final Remediation Construction Documentation Report concluded “… the completed final remedial action exceeds all design criteria and the plans and specifications… The remedial action reduced the volume, mass, toxicity, and mobility of the contaminated sediments in the Canal.”

Project Video

Related Services

  • Environmental Dredging
  • Geotextile Tube Dewatering
  • Geotextile Tube Dewatering Test (GDT)
  • Mechanical Dewatering
  • Dredging Water Treatment
  • Mobile Water Treatment System
  • Dewatering System Design

More Project Experience

Cedar Creek OU2A Remedial Action

Mill River Remediation

Stevens Point MGP Site Remedial Action Construction

See more remediation projects...

Recent Posts

2021 MWEA Virtual Biosolids Conference

March 29, 2021 |

Join IAI for the 2021 MWEA Biosolids Conference, a virtual training event providing up to 0.8 continuing education credits for Michigan wastewater operators. The conference will cover a wide range of issues facing wastewater utilities, related to biosolids handling and disposal.

IAI Names Martijn Luth, General Manager for Dredging & Sediment Dewatering Division

January 14, 2021 |

Please help us welcome Martijn Luth to the IAI team! Martijn will serve as General Manager for the Dredging & Sediment Dewatering Division.

IAI Welcomes Leslie Sorensen, P.E., to Engineering & Technical Services Division

November 4, 2020 |

Meet Leslie Sorensen, who has joined IAI as Senior Manager for the company’s Engineering & Technical Services (ETS) Division. Join us in welcoming Leslie, as well as celebrating the long career of Kent Trierweiler, as he prepares for retirement.

Latest Videos

Contact Us

info@iaiwater.com

616.866.1600

7888 Childsdale Ave. NE,
Rockford, Michigan 49341

Directions to our office

Services

  • Contract Operations, Maintenance & Management
  • Dredging
  • Sediment Dewatering
  • Dredging Water Treatment
  • Sediment Remediation
  • Coal Ash
  • Wetlands & Shorelines

Topics

geotextile tubes dredging water treatment contaminated sediment PCBs hydraulic dredging dredging HAZWOPER michigan water treatment coal ash environmental dredging Remedial Action NPDES

Like Us

This message is only visible to admins.
Problem displaying Facebook posts.
Click to show error
Error: Server configuration issue Error: No posts available for this Facebook ID

Copyright © 2026 Infrastructure Alternatives Inc. - All rights reserved. · Website by: Creative Solutions